Requirements for NET METERING

Published on April 27, 2022 01:04 PM 10325
NOTE: MUST HIRE A CEBECO 2 ACCREDITED BARANGAY ELECTRICIAN

A. TECHNICAL

  1. Letter of Intent
  2. Electrical Plan showing the Renewable Energy modification duly signed and sealed by a PEE
  3. Electrical Permit for Net Metering
  4. Site Sketch Plan
  5. Inverter Specifications
  6. Copy of test data and Test Certificates
  7. ERC COC Forms (with fee of Php. 1,500.00)

B. LEGAL

  1. SEC (for corporations) or DTI Registration (sole proprietorship)
  2. Sec-Cert. or BOD Res. (corp.), Authorization or SPA of authorized rep. (Sole prop.)
  3. Two (2) valid IDs of an authorized representative or signatory
  4. Photocopy of Declaration of Real Property and Lease Contract/Agreement (if rented property)
  5. Latest CEBECO 2 Receipt

C. MEMORANDUM OF NET-METERING AGREEMENT

NOTE: YOU MUST HAVE ALL THE DOCUMENTS FIRST

Please click to download the form: Net Metering Application Form